To ensure the quality of concrete stirring, concrete batch plants should be required Stir concrete mix, mixing time is short, fast unloading, the residual is less, low power consumption and less pollution.Stabilized Soil Mixing Plant The main factors affecting the quality of the concrete mixer stir: formal structure mixer, blender and mix feed tube geometry volume capacity ratio of the feed mixture and concrete batch plants feeding program position, mixing geometry configuration and arrangement of leaves, stirring speed and blade liner wear conditions.
1, should be empty before stirring commissioning.
2, according to the mixing time to adjust the time relay timer, to adjust in case of power failure.
3, the mixing tube and the water wet leaves and venue.
4, processes such as electrical or mechanical failure should occur unloading part of the mixing materials, reduce the load,cement concrete mixer troubleshooting and then drive operation.
5, when operating, should be inspected regularly to prevent electric shock and mechanical wounding accidents.
6, the test is completed, turn off the power, clean the mixing tube and venues cleaning.
Scale mixing station modest scale mixing station, mixing station with a total installed capacity to meet the needs of large quantities of concrete principles.
2014年7月17日星期四
2014年2月27日星期四
portable concrete batch plant and quantity of concrete mixers
Because has a wealth of experience in construction, known as Hunan climatic conditions, geological conditions , proficient in all aspects of the construction of highways , high-speed start from JIANXIN concrete plant manufacturers the balance Gui , along with team members on , seize the stage subsequent engineering focus and impact the key aspects of the construction , the construction will be divided across the board "focus on land acquisition and resettlement ," " assault dredging coverage" , " concrete quality defects governance" , "ahead of green construction ", " create a safe site ", "Engineering quality and Safety Year" , " quality and safety of looking back " , " JIANXIN cement concrete mixer construction ", " speed up civil mop "," road construction three standardized building " , " speed base construction "," socialist emulation "and 17 nodes control activities, early planning , given time , given task , and personnel , supporting the introduction of a series of incentive measures to ensure that every aspect of the project on time and smooth implementation of quality and quantity.